1)Which of the following is a phase of RAD model?
a)Business modelling
b)Data modelling
c)Application generation
d)All of the above
e)None of these
2)The UML Designation for a public class member is
a)the symbol @
b)the symbol #
c)the minus symbol(-)
d)the plus symbol(+)
e)the word public
3)A cross life-cycle activity of system development is
a)Data modelling
b)Fact finding
c)Prototyping
d)Data Flow Diagram modelling
e)Object Modelling
4)The term module in the design phase refers to
a)Functions
b)Procedures
c)Sub programs
d)All of the above
e)None of these
5)The objective of testing is
a)Debugging
b)To uncover errors
c)To gain Modularity
d)To analyze system
e)None of these
6)Software testing techniques are most effective if applied immediately after
a)Requirement specification
b)Design
c)Coding
d)Integration
e)None of the above
7)If limited user participation is available, which model is to be selected
a)Waterfall Model
b)Spiral Model
c)Iterative Model
d)Any of the above
e)None of these
8)Which of the following is the phase of SDLC in which the identified requirements are incorporated into the new system's design?
a)Maintenance
b)Physical Layout
c)Requirement Design
d)System Design
e) System Blueprint
9)Milestones are used to
a)know the cost of the project
b)know the status of the project
c)know the user expectations
d)All of the above
e)None of these
10)Software Quality is
a)Conformance to requirements
b)Fitness for the purpose
c)Level of satisfaction
d)All of the above
e)None of these
Answers:
1)d
2)d
3)b
4)d
5)b
6)b
7)d
8)b
9)a
10)d